38.6c New Delhi, India, Friday, September 20, 2024
Judiciary

NCDRC Directs Three C Shelters to refund Rs 12 Crores to homebuyers Due to Inordinate Delay in giving possession [Read Orders]

By Prachi Mishra      27 July, 2020 09:47 PM      0 Comments
NCDRCDirects Three C Shelters to refund Rs 12 Croresto homebuyers Due to Inordinate Delay in giving possession [Read Orders]

On Monday, 20th July 2020 The National Consumer Disputes Redressal Commission directed the developer i.e. Three C Shelters Pvt Ltd to refund 12 Crores (approx.)to the homebuyers in view of inordinate delay in giving possession for its Greenopolis Project in Gurgaon.

Presiding member Prem Narain noted, In these complaint cases, the possession was due in 2015-2016; however, even the construction is not complete.

The commission further stated Clearly the OPs have not been able to complete the project in time and to deliver the possession of properties in question to the respective complainants in time as per the allotment letter or the Apartment Buyer Agreement. It is now clearly established that the allottees have the right to ask for a refund if the possession is inordinately delayed and particularly beyond one year.

However, the builder argued that the complainant-buyer had breached the provision of the apartment buyer agreement as they have stopped paying the instalments so as per Section 55 of the Indian Contract Act, 1872 they are not entitled to any relief.

Regarding this the commission said:

Instalments have been paid up to the reasonable limit and the payment was stopped later on as there was no progress in the construction- therefore, it cannot be said that the complainants breached the agreement first and they are not entitled to any relief in the light of Section 54 and 55 of the Indian Contract Act, 1872.

The builder took the defence of Force Majeure for the delay, including the order of P&H HC in the case of Sunil Singh v, MoEF, Parayavaran, where a blanket was imposed on the groundwater for the use of groundwater in the region of Gurgaon and adjoining areas for the purposes of construction.

The commission remarked, Clearly, there was no ban on construction and OPs should have put their resources and managerial skills to bring water from outside and to complete in time.

The project was owned by Orris Infrastructure Pvt Ltd. which had entered into a development agreement with Three C Shelters Pvt Ltd.

The commission observed that the two companies had not entered into an agreement and therefore the development agreement was in question. It said Though this ground has not been taken by the complainants for seeking refund, however, this is also a valid ground for the complainants for seeking refunds. If there is uncertainty in the development agreement itself, as entered between Orris Infrastructure Pvt Ltd and Three C Shelters Pvt Ltd, the allottees would not like to block their money in such a project.

The company was directed to return the earnest money.

The commission also clarified that since Three C Shelters have received money and not Orris, Three C Shelters Pvt Ltd would be liable to refund the same to the complainantsalong with 9% p.a. interest from the date of respective deposits.

These observations were made in three orders, disposing of a batch of consumer complaints. In a few cases, the court directed the builder to hand over the possession by September 2020 with a penalty of 6%. If the possession is not made available by September 2020 then the homebuyers are at the liberty to seek a refund of their deposit.

 

[Read Orders]



Share this article:



Leave a feedback about this
TRENDING NEWS

delhi-hc-orders-mcd-to-pay-10-lakh-compensation-in-minors-death-case
Trending Judiciary
Delhi HC orders MCD to pay ₹10 Lakh compensation in minor's death case [Read Judgment]

Delhi HC directs MCD to pay ₹10 lakh for a minor's death due to negligence, applying res ipsa loquitur and affirming compensation for fundamental rights violations.

19 September, 2024 10:36 AM
sc-orders-release-of-convict-on-personal-bond-cites-injustice-in-denying-bail-due-to-inability-to-furnish-local-surety
Trending Judiciary
SC orders release of convict on Personal Bond, cites injustice in denying bail due to inability to furnish Local Surety [Read Order]

SC: Justice delivery mechanism must consider plight of indigent convicts unable to furnish local surety, orders release of convict on personal bond.

19 September, 2024 11:05 AM

TOP STORIES

rajasthan-hc-orders-10-year-passport-for-undertrial-in-matrimonial-dispute-cites-right-to-livelihood
Trending Judiciary
Rajasthan HC orders 10-year passport for undertrial in matrimonial dispute, cites right to livelihood [Read Order]

Rajasthan HC directs issuance of a 10-year passport to an undertrial in a matrimonial dispute, upholding the right to livelihood despite ongoing legal proceedings.

14 September, 2024 05:04 PM
himachal-pradesh-hc-clarifies-the-scope-of-section-482-crpc-in-compoundable-offences
Trending Judiciary
Himachal Pradesh HC clarifies the scope of Section 482 CrPC in compoundable offences [Read Order]

Himachal Pradesh HC clarifies that Section 482 CrPC cannot be invoked for compoundable offences when an alternative remedy under Section 320(1) is available.

14 September, 2024 05:36 PM
sc-bars-kejriwal-from-commenting-on-cbi-case-in-liquor-policy
Trending Judiciary
SC bars Kejriwal from commenting on CBI case in liquor policy

SC restrains Kejriwal from commenting on CBI case in liquor policy, grants bail with conditions, prohibiting visits to CM office and signing files.

16 September, 2024 10:33 AM
sc-rejects-plea-to-re-appear-in-neet-ug-for-not-being-allowed-to-carry-handkerchief
Trending Judiciary
SC rejects plea to re-appear in NEET UG for not being allowed to carry handkerchief [Read Judgment]

SC dismisses NEET UG candidate's plea to reappear due to a handkerchief ban, citing no significant impact on performance from hyperhidrosis during the exam.

16 September, 2024 10:37 AM

ADVERTISEMENT


Join Group

Signup for Our Newsletter

Get Exclusive access to members only content by email