38.6c New Delhi, India, Friday, April 26, 2024
Judiciary

Homebuyers Are Entitled For Refund Of Entire Principal Amount In Case Of Cancellation Of Delayed Flats

By LawStreet News Network      04 June, 2019 12:00 AM      0 Comments
Homebuyers Are Entitled For Refund Of Entire Principal Amount In Case Of Cancellation Of Delayed Flats

The National Consumer Disputes Redressal Commission (NCDRC) in a recent judgment has ordered real estate major Supertech to refund the entire amount of over Rs 1 crore to a homebuyer for delay of two years in delivering the house.

The order was passed by a Bench of Justice V.K. Jain on holding that a homebuyer cannot be forced to forfeit any amount deposited with a builder in case he seeks cancellation of allotment of flat for delay in construction.

While hearing an appeal, the Bench observed that in order to discourage homebuyers from cancelling allotment, builders always put stringent clauses in the agreement on forfeiture of a substantial amount deposited by buyers.

To this, the apex consumer commission held that real estate companies cannot invoke such harsh clauses in cases where the buyers are forced to seek cancellation due to inordinate delay in completion of any project.

Thus, it restrained Supertech from forfeiting 15% of the cost of the unit as cancellation charges after a buyer sought refund of money as the company failed to deliver the house in its Noida housing project by December 2016 as per the agreement.

The order was passed in favour of complainant Chandan Gupta, who had booked a residential flat with Supertech’s project ‘ORB Towers’ in Sector 74 of Noida for a consideration of Rs 2.36 crore.

As per the agreement, the flat was to be delivered to him by June 2016 or latest by December 2016 after including the grace period of six months. However, due to delay in handing over the possession within the stipulated period, Mr. Gupta sought cancellation of allotment and approached the commission after the developer refused to refund Rs 1.08 crore which he had deposited so far. As the commission directed that the amount be refunded to the buyer, the developer contended that it was entitled to forfeit 15% of the cost of the unit as cancellation charges as per clause 37 of the agreement between the parties.

The commission, however, rejected its claim saying there was no merit in the contention. “In my opinion, the aforesaid clause would apply to a case where the allottee, for his own reasons, seeks cancellation of the allotment and does not apply to a case where he is forced to seek cancellation of the allotment and refund of the amount paid by him to the developer on account of failure of the developer to deliver possession of the house within the time period committed. Had the complainant sought cancellation of the allotment before December 2016, by which the possession was to be delivered to him even after giving benefit of the grace period to the builder, there could have been some merit in the contention. But, he having filed the complaint after expiry of the aforesaid time-line, clause 37 of the agreement would have no application,” it said.

Accordingly, the commission directed Supertech Ltd to refund the buyer within three months the entire principal amount of Rs 1.08 crore along with compensation in the form of simple interest at 10% per annum from the date of each payment till the date of refund.



Share this article:

User Avatar
About:


Leave a feedback about this
TRENDING NEWS

plea-in-sc-seeks-sit-probe-into-electoral-bonds-scam
Trending Judiciary
Plea in SC seeks SIT probe into 'Electoral Bonds scam'

NGOs seek SC probe into Electoral Bonds, alleging pay-offs and quid pro quo between corporates and governments, demanding an SIT to investigate and recover proceeds of crime.

25 April, 2024 10:50 AM
cant-control-elections-or-issue-directions-on-suspicion-sc
Trending Judiciary
Can't control elections or issue directions on suspicion: SC

Supreme Court says it cannot control elections or be an authority over the Election Commission, deferring a judgement on 100% VVPAT counts.

25 April, 2024 11:48 AM

TOP STORIES

sc-orders-medical-examination-of-yr-old-rape-survivor-seeking-to-terminate-her-week-pregnancy
Trending Judiciary
SC orders medical examination of 14-yr-old rape survivor seeking to terminate her 28-week pregnancy

Supreme Court orders medical examination of 14-year-old rape survivor seeking termination of 28-week pregnancy. Decision to be made after evaluating impact on her health.

20 April, 2024 11:00 AM
a-critique-of-the-supreme-courts-adventurism-for-lgbtqia-rights
Trending Legal Insiders
Overreaching Jurisdiction: A critique of the Supreme Court's adventurism for LGBTQIA rights

In its over-enthusiasm to protect LGBTQIA+ rights, has the Supreme Court exceeded its constitutional mandate under Article 142? A Delhi University research scholar evaluates the theme.

22 April, 2024 10:48 AM
new-criminal-laws-watershed-moment-for-society-cji
Trending Legal Insiders
New criminal laws watershed moment for society: CJI [Read Inaugural Remarks]

CJI Chandrachud hails new criminal laws as a watershed moment, marking a significant overhaul for the justice system, emphasizing adaptation and technology's role.

22 April, 2024 11:26 AM
sc-grants-permission-for-medical-termination-of-pregnancy-of-14-yr-old-rape-survivor
Trending Judiciary
SC grants permission for medical termination of pregnancy of 14-yr-old rape survivor

Supreme Court grants medical termination of pregnancy to 14-yr-old rape survivor after assessing adverse health impacts, setting aside Bombay HC's decision.

22 April, 2024 12:14 PM

ADVERTISEMENT


Join Group

Signup for Our Newsletter

Get Exclusive access to members only content by email