New Delhi: The Supreme Court has set aside a Calcutta High Court Division Bench judgment that halved an arbitral award in favour of a dredging contractor against the Board of Trustees of the Port of Kolkata, and has restored the award in full. It held that a court under Section 37 of the Arbitration and Conciliation Act, 1996 cannot modify an award on the sole ground that the claim for additional work exceeded 70% of the original contract value, without any substantive reason showing a conflict with the “most basic notions of morality or justice”.
A Bench of Justice J.B. Pardiwala and Justice K. Vinod Chandran, in a judgment authored by Justice Chandran, heard two appeals (Civil Appeal Nos. 14303 and 14304 of 2026), one by M/s Marino Dredgeco Limited and the other by the Port Trust. The Division Bench had, in an appeal under Section 37 by the Port Trust, overturned the Section 34 judgment that affirmed the award, and cut the amounts payable to 50% of what the arbitrator quantified, with interest reduced to 6% on the principal sum from 08.02.2002. It did so even while recording that the award was not one based on ‘no evidence’ or ‘insufficient evidence’ and could not be termed perverse, patently illegal or against the fundamental policy of Indian law.
The contract was for dredging the river bed and shores at Sagar Island to make a channel and basin for a shore-based pilot station, to be completed within 18 months. The Court noted it was admitted that the original contract value was Rs 2,86,56,200, of which Rs 2,79,32,865had been paid, and that the arbitration was for additional work entrusted by a Port Trust letter of 19.07.2000. The contractor said that re-dredging was needed because of siltation, the soil data given by the Port Trust did not match, and protective walls were not built. The channel was put to use and inaugurated by the Port Trust’s Chairman on 17.04.2001, and the arbitral award is dated 03.11.2003.
Senior Advocates Mr. R. Anand Padmanabhan and Mr. Amitava Mukherjee, for the contractor, argued that the jurisdiction under Section 37 is limited, as held by the Constitution Bench in Gayatri Balasamy v. ISG Novasoft Technologies Ltd., 2025 INSC 605, and that the modification rested on a subjective presumption. Senior Advocate Mr. Siddharth Bhatnagar, for the Port Trust, sought to set aside the whole award, or in the alternative to keep the 50% reduction, saying no completion certificate was issued and no additional work was entrusted, and relied on Batliboi Environmental Engineers v. HPCL, (2024) 2 SCC 375. The Court noted that Batliboi dealt with damages and not with invoices raised for additional work.
The Court held that the additional work of re-dredging was “identical” to the original work, and that the Division Bench had itself found that the absence of a completion certificate, which the Port Trust did not issue, does not disentitle the contractor to its bills, that the quantification was based on joint measurements and pre- and post-work levels produced by the contractor, and that additional work was necessitated by force majeure conditions and the mismatch in soil data. The modification of the award for the ‘shocking’ quantum, it held, does not fall within the contours of Section 37.
Referring to Ssangyong Engineering & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131, the Court said that the words ‘shocks the conscience of the Court’ are not to be applied as lip service, and that there must be a substantive reason that blatantly and patently brings forth the conflict. It added, citing Somdatt Builders–NCC–NEC (JV) v. NHAI, (2025) 6 SCC 757, that a court under Section 37 cannot set aside an award merely by using expressions such as ‘public policy’, ‘patent illegality’ and ‘shocking the conscience of the Court’.
On partial modification, the Court noted Gayatri Balasamy permits setting aside an award in part only where the valid and invalid portions are separable, and found here that the quantification, based on measurements and invoices of one character, cannot be compartmentalised. It said the Division Bench had not examined the measurements or invoices, which would anyway be a merits review barred by the Act. It also held that a quantum cannot be reduced just because the award debtor is a Government entity, citing Pam Developments Pvt. Ltd. v. State of West Bengal, (2019) 8 SCC 112:
“There can hence be no interference caused to the quantum of claim decided by the Arbitrator, based on valid material, merely for the reason that the award debtor is a Government entity and that the quantum appears to be excessive without any substantiation for such a ground being raised against the award itself.”
The impugned judgment was set aside, the contractor’s appeal was allowed and the arbitral award stands restored. The Port Trust’s appeal was disposed of as a consequence.
Appearances:
For the Contractor: Mr. R. Anand Padmanabhan and Mr. Amitava Mukherjee, Senior Advocates.
For the Respondent (Board of Trustees of the Port of Kolkata): Mr. Siddharth Bhatnagar, Senior Advocate.
Case Title: M/s Marino Dredgeco Limited vs. The Board of Trustees of the Port of Kolkata, Civil Appeal No. 14303 of 2026 (arising out of SLP (C) No. 15175 of 2025) with Civil Appeal No. 14304 of 2026, 2026 INSC 1238